Payload Changeout Room Supports Last Shuttle Cargo
07.07.11
After 29 years of supporting space shuttle missions, the payload
changeout room, or PCR, at NASA Kennedy Space Center's Launch Pad 39A
has been used for the last time to install cargo into a shuttle's
payload bay.
The canister containing the Raffaello multi-purpose logistics module, or
MPLM, was hoisted into the PCR on June 17 and the MPLM transferred into
space shuttle Atlantis on June 20.
As part of the rotating service structure, or RSS, the PCR is an
enclosed, environmentally controlled area that supports payload delivery
and servicing at the pad and mates to the shuttle's cargo bay for
vertical payload installation. Clean-air purges help ensure that
payloads being transferred from a payload canister into the PCR are not
exposed to the open air.
Although there was a PCR on both Launch Complex 39 pads, the first 24
shuttle missions lifted off from pad A while pad B was being
transitioned from an Apollo to a shuttle pad.
The payload for the STS-4 mission was the first shuttle cargo to be
installed from a PCR, arriving at the pad May 22, 1982, a few days
before shuttle Columbia's rollout on May 26.
Greg Henry, United Space Alliance, or USA, deputy director of solid
rocket booster manufacturing operations, was the pad's first payload
move director and supported the first payload transfer from the PCR,
which was for the STS-4 mission.
"STS-4 carried a primary Department of Defense payload, DoD 82-1," Henry
recalled, "which was a classified instrumentation pallet."
The STS-4 cargo manifest also included the first university student
experiments, known as Get Away Specials, and the first commercial
experiment, which utilized the Continuous Flow Electrophoresis System,
or CFES.
"At the pad, the payload canister is lifted and mated to the PCR," Henry
explained. "The PCR and canister doors then are opened and the payload
is transferred to the payload ground-handling mechanism, or PGHM, a
movable payload handling mechanism that is supported by overhead rails
in the PCR."
The PGHM has platforms positioned at five levels to provide access to
the payload when it is installed on the mechanism and the orbiter
payload bay. Each platform has extendible planks that can be configured
to accommodate a particular payload.
"That first transfer was the only one done using the original
configuration of the PGHM," Henry said. "The original design proved to
be operationally impractical for larger multi-payload transfers."
Henry said a major redesign was required of the PGHM front support beams
and support fittings that replaced mechanical jack screw operated
J-hooks with the current hydraulic cylinder actuated hooks and control
panels.
"The design was completed prior to STS-4 pad flow and the actual
modification to the PCR and PGHM was accomplished between launch of
STS-4 on June 27 and arrival of the STS-5 payloads on Oct. 12," Henry
said. "In less than four months, the team replaced the old PGHM payload
support beams with stronger beams and support hardware."
They also installed an all new hydraulic system, including pump package
control panels, hydraulic lines and J-hook fittings, completed a system
proofload, and conducted a validation transfer using payload mass
simulators.
"It was an incredible accomplishment in a very short period of time," Henry said.
Richard Jacques, USA lead payload technician for advanced systems, has supported work in the PCR since 1989.
"Since 25 to 30 technicians are needed to transfer the payloads into the
orbiter, the payload shop utilizes technicians from the entire launch
pad," Jacques said.
"The Hubble Space Telescope launch and servicing missions were the most
difficult because the clean room criteria was stricter. We put in many
more hours than usual, cleaning every nook and cranny. More attention
was paid to anything that would be touched. We even used 'clean-room'
paper for any documents needed in the PCR and Kapton tape designed to
reduce the tape's outgassing."
Pete Reutt, USA payload mechanical engineer, also started in 1989 and
recalled the challenges of payload processing for the Hubble missions.
"Although these were highly sensitive clean missions and we had to go
above-and-beyond normal cleaning procedures, it was rewarding to see the
telescope filling the payload bay, all by itself, enclosed in its shiny
silver blankets and panels. It was an especially beautiful payload,"
Reutt said.
"Support for STS-125, the last Hubble servicing mission, was
particularly complex. The fluid lines and cables had to be connected in
the PCR the whole time the payload was undergoing testing, right up
until closeout."
Not all of the excitement in the PCR came as a result of normal payload
processing operations, Jacques recalled: "After 9/11, a public
announcement was made that an inbound aircraft had been spotted in the
vicinity of the pad, requiring a complete pad evacuation. We had to safe
the systems, get people out of their body harnesses and egress out of
the clean room quickly, still wearing our bunny suits (clean-room
attire). As it turned out, the alarm was caused by a small aircraft
flying down the coastline with its radio turned off. That was a day to
remember!"
Following Atlantis' final launch on the STS-135 mission, the fixed and
rotating service structures on pad A will be dismantled. The pad
surface, though, is planned to be used to support the liftoff of future
rockets carrying NASA astronauts into space.
Kay Grinter
NASA's John F. Kennedy Space Center